Sent from the Village of Wilmette:

December 6, 2019

Dear Wilmette Resident:

DiMeo completed the storm sewer installation on Washington December 4, 2019. Storm sewer work began on Lamon on December 5, 2019. All storm sewer work on Lamon will be completed December 12, 2019. Temporary pavement patching on Washington will begin Friday, December 6, 2019.  All storm sewer trenches including Lamon will be paved by December 13, 2019.
We regret any inconvenience the construction may bring and thank you for your patience throughout this process.

Should you have any questions or concerns about the project or any upcoming work, please do not hesitate to contact the project team on the website www.wsnsp.com or the Resident Engineer Tracy Wais, PE, at 847-878-0501 or twais@cbbel.com.